The exclusion process involves evaluating whether the bidder has committed any offences that would lead them to be excluded from the bidding process.
The exclusion questions you can ask are split into two types:
It is considered best practice to ask bidders both types of questions in Route 3 procurement exercises.
The table below provides an overview of both types of exclusion criteria.
Exclusion Criteria in Route 3 Procurement Exercises |
Must ask | May ask |
Self-Cleansing Applies |
Criminal Convictions |
|
|
|
Blacklisting |
|
|
|
Tax and Social Security Breach (Binding decision - judicial or administrative)* |
|
|
|
Tax and Social Security (Decision by any other means)* |
|
||
Environmental, Social and Labour Law |
|
|
|
Bankruptcy and Insolvency |
|
|
|
Grave Professional Misconduct |
|
|
|
Conflict of Interest |
|
|
|
Distortion of Competition |
|
|
|
Contract Deficiencies |
|
|
|
Misrepresentation |
|
|
|
Unduly Influence |
|
|
*In the case of tax and social security breaches, where self-cleansing does not apply, the bidder should not be excluded if they:
The bidder must be given the opportunity to provide evidence that they have taken sufficient and appropriate remedial action i.e. they have ‘self-cleansed’. If you are satisfied that the evidence they have given is sufficient to demonstrate reliability, you should not exclude the bidder from the procurement procedure on those grounds.
The bidder must satisfy that it has:
In the case of tax and social security breaches, the bidder should not be excluded if they have fulfilled their obligations by paying or have entered into a binding agreement with the view to paying monies, due or the obligation to repay otherwise ceases.
When considering any self-cleansing measures, organisations must consider all relevant factors. This includes the gravity and particular circumstances of the criminal offence or misconduct.
If you believe the bidder’s remedial action is insufficient to demonstrate reliability, you must provide them with a statement outlining the reasons for the decision. This must be provided in writing as soon as is reasonably practical to allow the bidder to understand why the self-cleansing measures they have taken are insufficient.
Questions relating to exclusion grounds are contained in the SPD. You must use the SPD for all Route 3 procurements. More information on the SPD and the Standardised Statements is contained in the SPD station.
A document containing a set of "standardised statements" has been developed to support you in explaining the exclusion criteria to bidders. Within the standardised statement document, is information that can be added to your contract notice in section II.2.14 (Additional Information) The Standardised Statements document can be found at the bottom of the page.
Please note that if you use the online SPD module on PCS, there is no need to add information on the Exclusion Grounds to the Contract Notice as they are automatically added to the module.
The buyer must ask the bidder questions relating to criminal convictions and blacklisting in all Route 3 procurement exercises. If the bidder confirms they have taken part in these activities, they must be excluded from the process if they have not taken sufficient self-cleansing actions.
These are contained in regulation 58(1) and (3) of the Public Contracts (Scotland) Regulations 2015.
Buyers must ask if a bidder has been convicted by final judgement of one of the criminal offences contained in the relevant regulations.
This includes:
Buyers must ask if a bidder has taken part in blacklisting activities.
Blacklisting is the practice of systematically denying individuals employment who would otherwise be able to be employed.
Blacklisting is done on the basis of information, accurate or not, held in some type of database. The Scottish Government regards blacklisting or the compiling of a blacklist as totally unacceptable.
The Employment Relations Act 1999 (Blacklists) Regulations 2010 provide rights for individuals if blacklisting results in refusal of employment, detriment, dismissal or redundancy.
The Scottish Government treats tax and social security obligations seriously.
Organisations must exclude bidders where they have been subject to a binding decision (judicial or administrative) which found a breach of legal obligations to pay tax or social security contributions. A judicial decision is one which is made by a court or tribunal. An administrative decision is one which is made by the relevant tax authority in the UK or in the country where the bidder is established.
In exceptional circumstances, you may disregard the mandatory exclusion grounds when selecting a bidder. This can only be done where there are overriding reasons relating to the public interest. This provision is known as derogation from the mandatory exclusion considerations. This allows buying organisations to respond to unforeseen emergency circumstances.
There is no definitive list of situations in which this derogation can be used, so any decision you make should be done carefully and on a case by case basis. Organisations should be able to demonstrate that the actual or potential harm is so great, that the public interest in using the derogation outweighs the public interest in excluding the bidder.
An example may be where urgently needed vaccines or emergency equipment can only be purchased from a bidder to whom one of the mandatory exclusion grounds otherwise applies.
Each situation must be judged individually, but the following situations are, on their own, unlikely to meet this test:
Organisations may exclude a bidder where the bidder has breached its tax or social security obligations and the decision has been reached by means other than a binding decision (judicial or administrative).
Buyers can request the following examples of evidence to understand a bidder’s breach in tax or social security obligations:
In the case of tax and social security breaches, the bidder should not be excluded if they have fulfilled their obligations by paying or have entered into a binding agreement with the view to paying the money due or the obligation to repay otherwise ceases.
Note – these examples relate to the UK tax regime, and there will be equivalents in other countries, which should be considered when relevant.
One of several discretionary grounds for exclusion relates to social, environmental and employment law obligations. These obligations include any relevant legislation, as well as relevant collective agreements and specific international agreements.
As these laws are wide ranging, you can focus on a specific area of law that bidders must take into account when making their self-declaration in respect of exclusion grounds. For example, breaches of employment and equality legislation.
Bidders may be excluded where your organisation can demonstrate that the bidder has breached any of these obligations. This exclusion ground is discretionary and it is therefore for your organisation to decide if exclusion is appropriate.
When determining whether to exclude a bidder on this basis, you should be proportionate in your decision, taking into account the size of the contracts, the relevance of the breach, and its impact on the operational and reputational risk to the delivery of the contract and reputational risk to the organisation.
Further information can be found in the Public Contact (Scotland) Regulations 2015 57 (2).
Where a bidder is bankrupt or subject to insolvency proceedings, you can choose whether to exclude them from the procurement exercise.
Potential evidence you could request to evaluate the situation include:
When considering whether to exclude such a bidder you should consider contract delivery potential risks, such as:
Additionally, you should take into account the potential benefits of awarding a contract to such a bidder. These can include:
Bidders may be excluded if they are guilty of grave professional misconduct, which renders its integrity questionable.
Further information can be found in The Public Contracts (Scotland) Regulations 2015, 58 (8) (c)
When determining whether to exclude a bidder on this basis, your organisation should be proportionate in its decision, taking into account the size of the contract, the relevance of the breach, and its impact on the operational and reputational risk to the delivery of the contract and reputational risk to the organisation.
Bidders may be excluded if a conflict of interest exists that cannot be effectively remedied by other less intrusive measures, and that may impact the procurement process.
Further information can be found in The Public Contracts (Scotland) Regulations 2015, 58 (8) (e)
When determining whether to exclude a bidder on this basis, your organisation should be proportionate in its decision, taking into account the size of the contract, the relevance of the breach, and its impact on the operational and reputational risk to the delivery of the contract and reputational risk to the organisation.
Bidders may be excluded if a distortion of competition arises from
Further information can be found in The Public Contracts (Scotland) Regulations 2015, 58 (8) (d) (f)
When determining whether to exclude a bidder on this basis, your organisation should be proportionate in its decision, taking into account the size of the contract, the relevance of the breach, and its impact on the operational and reputational risk to the delivery of the contract and reputational risk to the organisation.
Bidders may be excluded if they are found to have:
the bidder has:
Further information can be found in The Public Contracts (Scotland) Regulations 2015, 58 (8)(h)(i)
Bidders may be excluded if they have shown significant or persistent deficiencies in the performance of a substantive requirement under a prior public contractor or a prior concession contract which led to early termination of that prior contract, damages or other comparable sanctions.
Further information can be found in section 9 of The Public Contracts (Scotland) Regulations 2015 58(8)(g)
When determining whether to exclude a bidder on this basis your organisation should be proportionate in its decision, taking into account the size of the contract, the relevance of the breach, and its impact on the operational and reputational risk to the delivery of the contract and reputational risk to the organisation.
Bidders must not be excluded indefinitely from participating in procurement activity.
A bidder must only be excluded:
Organisations must consider how, in conducting a procurement, they can facilitate the involvement of small and medium enterprises, third sector bodies and supported businesses in that process. This can include the use of sub-contractors to support the delivery of the contract.
Organisations can, at their discretion, require verification of whether there are any grounds for the exclusion of any sub-contractor involved in the delivery. Where this information is sought the SPD must be used.
Where this verification shows that there are mandatory grounds for the exclusion of a sub-contractor, the organisation must require that they are replaced.
You should keep in mind that this only applies to sub-contractors upon who the main bidder is not relying on to meet the selection criteria of the contract.
Where there are discretionary grounds for the exclusion of a sub-contractor, the organisation can choose whether it should be substituted. Organisations must decide whether to apply discretionary exclusion grounds to sub-contractors involved in the contract delivery on a case by case basis, taking into account the various circumstances of the contract.
Exclusion grounds apply to a person who is:
In the Standardised Statement document, along with the selection statements, you can find two exclusion ground statements:
In the case of a Route 3 procurement, please make sure that you copy over the statement for an above threshold Contract Notice exclusion statement to the textbox in the Contract Notice under II.2.14 Additional Information. This will make sure that you have informed the bidders that you will apply mandatory and discretionary exclusion grounds in the procurement exercise.
Please note that if you are using the online SPD module in PCS, there is no need to include this in the contract notice.
The mandatory exclusion grounds (regulation 58(1) and (3) of the Public Contracts (Scotland) Regulations 2015) must be applied to all procurements, and you can also choose to apply the discretionary exclusion grounds.
Exclusion statements should be put under II.2.14 Additional Information of the Social and other Specific Services Contract Notice or detailed in the online SPD Module on PCS if it is being used.
(file type: doc)
An exit strategy is necessary to:
It should be a ‘front end’ activity i.e. considered when developing your commodity/service strategy.
Your exit strategy should be included in the Procurement Documents and contractual terms and conditions where possible. This may appear counterintuitive, but you need a strategy which is consistent with your overall sourcing strategy. Otherwise you risk being locked into an unsatisfactory contract. You may be forced to pay more to stop the contract to minimise operational impact.
Having an exit strategy in place at the start of a supplier relationship, means that any transfer requirements (e.g. intellectual property; systems access or handover process for delivery requirements etc.) will be included in the contract. This ensures minimum business and customer disruption if the relationship were terminated.
Please note: you cannot terminate a contract with the aim of avoiding procurement rule obligations.
Exit strategies should be reviewed annually, or when significant change occurs.
There are several considerations to be made when developing an exit strategy, including:
Below suggests some factors for consideration. This is not an exhaustive list as each contract / supplier relationship should be considered on its own merits.
An exit strategy should set your service requirements when the parties are transitioning out of the relationship. These requirements may include:
Data privacy and security are critical. The exit strategy should consider provision for:
Strict documentation and knowledge transfer contract requirements will be advantageous. Be sure to:
Transition, termination and timing are a key part of the financial aspects of an exit strategy. Be sure the contract:
An exit strategy should cover personnel issues, such as:
Your exit strategy must allow you to terminate a contract during its term where the following occur:
Regulation 73 of the Public Contracts (Scotland) Regulations 2015 requires the above termination grounds to be included as a contract term. If they are not included, they are implied.
Checklist
What you Need to Do |
Points to Consider |
Met? |
Administration of the contract is important
Contract administration is concerned with the mechanics of the relationship between the customer and provider.
Its importance should not be underestimated. Clear administrative procedures ensure that all parties to the contract understand who does what, when and how. |
The elements that need managing are likely to include:
|
|
Maintain the contract documentation. The contract will have to evolve to reflect changes in arrangements. Contract maintenance means keeping the documentation up to date and relevant to what is happening on the ground. Maintaining contract documentation is an important activity. |
Establish procedures to keep contract documentation up-to-date (including how to store/archive documentation). Ensure all contract documents are consistent, and that all parties have the correct version. |
|
Changes must be controlled.
Changes to services, procedures or contracts may have an effect on service delivery, performance, costs and on whether the contract represents value for money. The specification and administration of change control is an important area of contract administration. |
Appropriate structures need to be in place with representatives from both customer and supplier management sides to review and authorise change requests.
Be careful that changes do not fall outside the scope of the original PCS advertisement and conflict with procurement regulations – seek advice if you are unsure.
It is particularly important that additional demands on the supplier should be carefully controlled.
Formal authorisation procedures will be required to ensure only those new requirements (that can be justified in business terms) are added to the service. |
|
Make sure management understands what is happening.
Management reporting procedures ensure that information about contract problems reach those with power to act as soon as possible. |
Requirements for service performance reports and management information should be built into the contract and confirmed at the tender stage.
Where possible, you should make use of your Organisation's own management information and performance measurement systems.
For many business managers a summary of the service they have received along with a note of exceptions is normally sufficient.
Information requirements may change over the life of a contract. |
|
|
|
|
|
|
Blank rows are provided for your use e.g. to add additional checklist items.
Allowing and regulating contract variations should be a standard feature of all contracts. Although a supplier may request a contract variation, the ability to vary the contract must be approved, managed and controlled by the customer.
You should provide a method for contract variations to be agreed between the customer and the supplier. This should be in writing through a formal amendment of the contract. This practice is also known as a "change management process", "change control procedure" or something similar.
It is critical that no-one involved in managing and administering the contract agrees to informal contract amendments on their own. All potential contract variations/changes must be fully explored with the appropriate contract managers/stakeholders. Any agreed variations should be undertaken in line with the change management process.
The reasons for the variation should be clearly documented. Variations should not be used to mask poor performance or serious underlying problems. The variation impact on original timeframes, deliverables and value for money should be assessed. If the effects are significant, senior management and other stakeholders must be consulted.
Variations should be planned accordingly. Customers should be aware of the risk that multiple contract changes make to a contract over time i.e. this may shift the overall allocation of contract risk or transfer particular risks to your Organisation.
It is important to analyse all consequences of a proposed contract amendment. Make sure there are no detrimental effects to the contract or service levels.
Contract managers must ensure contract variations do not significantly change the contract's requirement and/or substantial parts of the original agreements made during the tender and mobilisation stages. This is referred to as a ‘substantial modification’ under The Public Contracts (Scotland) Regulations 2015. If this is the case, you must undertake another procurement exercise. This is because the revised arrangements are substantially different from those selected through the original procurement. If a new procurement if not undertaken your Organisation may be open to challenge from another supplier.
Quickfire Guide
Do |
Don't |
Assess value for money of the variation(s)
|
Change the original contract requirements i.e. there is no substantial modification. |
Assess the effect of the variation on the original contract e.g. no detrimental effects on timeframes and deliverables.
|
Use variations to hide poor performance or serious underlying contract problems. |
Consult senior management/stakeholders if variation(s) are significant. Follow your organisations governance procedures. |
Agree to contract variations on your own.
|
Clearly document the reason(s) for the variation and the amendment in writing. |
|
Inform customer(s) of the contract change(s) |
|
Checklist
Key issues to consider in managing contract variations include:
Key Areas |
Achieved? |
Are procedures required by the contract being followed? |
|
Have the reasons for the proposed variation been assessed? Does this indicate an emerging or actual problem? |
|
Has the impact of the proposed variation on the contract's deliverables been assessed? Particularly whether the variation or the work it represents is actually required and is already part of the original contract deliverables? |
|
Has the effect of the proposed variation on the contract's price been determined? |
|
Has authority been given for making the variation? |
|
Has the variation and its impact been properly documented? |
|
Have you undertaken all reporting requirements? |
|
|
|
|
|
Blank rows are provided for your use e.g. to add additional checklist items.
For above threshold contracts, the starting position is that contract changes will require a new competition to be held. This is unless one of six exceptions can be applied. These exceptions are:
Quickfire Guide
When making successive modifications you must take care that the cumulative value of these does not breach any of the previous requirements. This does not apply in the case of point 3, where successive modifications would, by definition be unrelated and so the value limitation of successive modifications does not cumulate.
If planned modifications are determined not to meet the criteria, or have not been provided for in the original contract documentation, then a new procurement procedure must be undertaken. Legal advice should be sought. For more information on contract modification during the term of the contract, please see Regulation 72.
There are a variety of issues that should be considered in any change management process to ensure that it is effective. Three key areas for consideration are:
the need for change impact reports;
any pricing principles that will apply to the change; and
the supplier's obligation to undertake the change.
Where the consequences of getting things wrong are significant and it is recognised that a change is required, it makes sense to run a formal pilot. If the pilot fails to meet expectations, you can revisit and retest until you achieve the required results. This can be done before committing your resources to, and reputation on a wider scale contractual change.
For example "Plan, Do, Check, Act" (PDCA) is a recognised continuous improvement plan (CIP) model. It can be utilised to ensure your change will deliver the desired results. As its name indicates, there are 4 steps to the model of which steps 2 and 3 can be repeated until the desired result is achieved. The 4 steps can be summarised as:
Quickfire Guide
Plan: Define the problem to be addressed. Collect the relevant data. Ascertain the problem's root cause
Do: Develop possible solutions. Select the most appropriate solution(s). Implement a small-scale pilot solution. Decide upon a measurement to gauge effectiveness of the pilot.
Check: Check the problems you have encountered during the pilot and identify the root causes. Measure how effective the solution has been by comparing pre-pilot and post-pilot data. Depending on the success of the pilot, you have the option of repeating the “Do” and “Check” phases. You can incorporate additional improvements until you get the desired result
Act: You can implement your solution. However, if you are using the PDCA as part of a continuous improvement initiative, you need to loop back to the Plan Phase (Step 1), and seek out further areas for improvement.
A detailed Change Management Process is of little value if the change required has been determined, and the supplier refuses to implement. Accordingly, the Change Management Process may mean the supplier cannot unreasonably refuse (either directly or indirectly) a change requested by the Organisation.
Unreasonable grounds for refusing a change might include:
demanding unreasonable charges for the change;
imposing unreasonable conditions for undertaking the change; or
refusing to include the change under the agreement. This could be despite the subject matter being reasonably related to, or connected with, the services.
A carefully drafted Change Management Process can mean the difference between what the customer requested in terms of systems/services, and what they discover is actually needed during the term of the contract.
Before any change request can be properly considered, the customer and the supplier must understand the implications of the proposed change. To support this you may require the service provider to prepare an impact report. (The service provider will normally be in the best position to assess the likely impact of a change). Ideally, the impact report will present a full description of the change, including how the change is to be implemented and, where relevant, detail:
You should specify how costs associated with any change will be allocated between your Organisation and the supplier(s). This should be done as part of the Change Management Process.
Ordinarily, the Organisation should be required to pay for a change when the change is not considered to be within scope of the existing contract.
Where a change falls outside the scope of the existing contract, the Change Management Process may detail the principles that will determine the price to be paid by the Organisation. For example, the Change Management Process may stipulate that the price for any change should be:
The Change Management Process may enable the Organisation to request the supplier to provide an auditor's certificate. This could confirm that the pricing of any change complies with the pricing principles.
It is possible for an Organisation to terminate a contract during its term. These circumstances are covered in the Exit Strategy Station.
Please note: you cannot terminate a contract with the aim of avoiding procurement rule obligations.
This section outlines a number of activities and tools necessary to manage and improve suppliers’ performance.
You must be careful not to substantially modify the contract when considering some of the following.
Benchmarking costs against the suppliers’ competitors is a recognised method of avoiding cost ‘creep’ and ensuring best value.
Benchmarking should be undertaken throughout the life of the contract. It can be used for:
This 80 percent will normally be no more than 20 percent of the number of line items.. You now have a manageable amount of data to go out into the market place with.
This does not cover every aspect of the potential scope of supply. In certain circumstances additional items may need to be added, such as bottle-neck and specialised items. The aim is to gain an estimation of the market rates.
The incumbent supplier should be made aware that you are planning to perform a benchmarking exercise before you go out to the market place.
Benchmarking is generally an informal process and the Management Information Hub is a good source of information, as is the internet. You can also contact a number of suppliers directly. However it is important to ensure that these suppliers who receive requests for information understand that you are conducting a benchmarking exercise and that this is not a business opportunity. The request should be simple enough for the suppliers to provide the information without having to spend a great deal of time doing so.
If you are not comfortable with where the incumbent supplier’s pricing fits, invite them to a meeting. Give them the opportunity to explain why they are not competitive against the current market rates. On no account should you divulge the competitors' names or pricing information.
If the supplier is willing to accept their prices are not in line with the market rate, this will be a relatively pain free cost reduction for you. If the supplier is unwilling to negotiate a reduction, you should initiate the escalation process. Include this as an agenda item at the next Review Meeting.
The fundamental purpose of Contract and Supplier Management is to ensure that:
Anyone engaged in managing suppliers must read and fully understand the contract terms and conditions. This will ensure they are not at a disadvantage should any issues arise.
It is essential that your Organisation’s Contract Manager/ Contract Management Officer is engaged from the Develop Strategy stage early in the process and participates in the development of the terms & conditions.
The Full Balance Scorecard is recognised for monitoring and managing contract and supplier performance.
KPIs provide a mechanism to measure the four quadrants of the balanced scorecard (Quality, Cost, Sustainability, and Service). KPIs help organisations understand how well they and/or their suppliers are performing against their strategic goals and objectives.
For Care & Support Services please also read the Additional Guidance when Reviewing a Care and Support Service.
Contract management arrangements should identify what happens when the contract is not being delivered as agreed or, the agreed quality standards are not being met.
Blacklisting refers to the practice of systematically denying individuals employment who would otherwise be able to be employed. This can be on the basis of information, accurate or not, held in some type of database.
The Scottish Government regards blacklisting or the compiling of a blacklist as unacceptable.
Effective contract management ensures the practice of blacklisting does not occur in public contracts.
The Employment Relations Act 1999 (Blacklists) Regulations 2010 provide rights for individuals if blacklisting results in refusal of employment, detriment, dismissal or redundancy.
Any bidder which has been found to have breached, or has admitted breaching, these Regulations must be excluded from the procurement process for a period of three years. This is unless it can demonstrate to you that it has taken appropriate remedial steps. The Scottish Government regards blacklisting or the compiling of a blacklist as totally unacceptable. Blacklisting refers to the practice of systematically denying individuals employment, who would otherwise be able to be employed, on the basis of information, accurate or not, held in some type of database.
MI is used to monitor the supplier's or contract's performance. It ensures management have the information necessary to make effective strategic and operational decisions.
It is important that your MI requirements are clearly defined and communicated to the supplier. The reporting arrangements can be included in your specification and/ or in the terms and conditions of the contract. Reporting arrangements must be fair and proportionate and not duplicate information already provided.
Your MI approach should minimise demands on suppliers for information about goods/ service delivery. The frequency and level of reporting should be informed by a risk assessment. Reporting may increase in certain circumstances, for example, if a complaint is made about service/ delivery.
For some specific services you should avoid duplicating information which is collected by and is available from regulatory bodies. This can be achieved through the development of Memoranda of Understanding and regular discussions between the Organisation and the regulatory bodies.
Contract Managers/ Contract Management Officers should present information gained through contract management in regular reports to senior managers. In order to fulfil their role, they should:
Further examples can be found in the Management Information document.
Sustainable Procurement outcomes, for example Fair Work Practices, must be an integral element of the contract and supplier management process. They should be included as a standard agenda item at supplier review meetings and considered alongside all other contract management matters.
It is important to ensure monitoring includes the use of any agency or sub-contractor workers throughout the duration of the contract. This will include any new members joining the workforce engaged on the contract's delivery.
Evidence should be sought from suppliers to demonstrate compliance with agreed contract conditions. This includes what the main contractor is doing to ensure Sustainable Procurement outcomes, such as Fair Work First commitments, down the supply chain to subcontractors and to agency workers. Evidence which should be sough can include, reviewing recruitment information which could include pay policy and the terms and conditions for workers involved in the delivery of the contract.
Where there are material concerns regarding a supplier’s compliance with any sustainable procurement commitments or the contractual obligations it has made, an Organisation could consider whether to undertake general sustainability audit of the contract.
Contract management arrangements should identify what happens when the contract is not being delivered as agreed or, the agreed quality standards are not being met.
Incentives and sanctions should be used appropriately to maintain/improve the contract/supplier performance.
There are specific contract terms and conditions (T&Cs) that can be used to help drive contract compliance/performance. These should be incorporated into the contract T&Cs.
You should ensure that you understand the contract's specific T&Cs. Any incentives and sanctions must be appropriate and legally enforceable. You must seek legal advice if you are in doubt as to the wording, appropriateness or legality of a proposed condition.
Examples of incentives and sanctions which could be considered are listed below. These must not be applied autonomously. Appropriate internal approval must be sought and received prior to implementation.
Incentives could (subject to avoiding substantial modification) include:
For a sanction to be effectively enforced, sufficient evidence is required to justify the claim or action. It is therefore important to have clear records which could include records of; agreed service levels; notice periods; reminders; communications; agreements etc.
Any enforced incentive or sanction must comply with the agreed terms and conditions for the contract or agreement.
Improvement opportunities can be identified by anyone engaged with the Organisation, both internally and externally.
Many improvement ideas can come from management, employees and supplier(s) operationally involved in the delivery of the service/ goods contract. Supplier(s) and employees can be particularly insightful as they are regularly exposed to operational inefficiencies which may not be visible higher up in the Organisation.
Your Organisation should seek feedback and should work to develop a culture where everyone in the Organisation is encouraged to look for, and suggest, operational improvements. All suggestions should be considered.
A key element of Contract and Supplier Management is the proactive identification and management of risk. Guidance can be accessed on the Risk Management page.
More guidance on fraud can be found in the Scottish Government website on Fraud.
Weak interactions between an Organisation’s finance, commercial, and contract management functions provide an opportunity for fraud and overbilling. This could be as a result of error and inefficiency, or by deliberate intent.
Without basic scrutiny of payments and performance an Organisation’s departments may rely on the supplier to interpret the contract correctly which may result in errors . Better scrutiny of payments and improved contract knowledge within your Organisation will identify any possible overbilling and fraudulent activities Organisations can then take appropriate action.
Contracts are awarded following a thorough evaluation process which addresses some standard elements.
Throughout the life of the contract, your Organisation’s Contract Managers/Contract Management Officers should perform periodic supplier ‘health checks’. This ensures the standards demonstrated during the initial evaluation are being maintained. Health checks could include:
The frequency of the checks should be in line with the type of contract. For example, strategic and bottleneck contracts will be checked more frequently than collaborative and routine contracts.
Contract management activities must include sufficient checks to ensure suppliers are meeting their Data Protection Legislation obligations as the Processor. These checks may include audits undertaken by the controller or a third party auditor.
If obligations are not being met, organisations should take urgent remedial action with the supplier to address issues and risks.
More detailed information can be found in Additional Resources.
Good Contract and Supplier Management processes should encourage both supplier and organisational innovation. It should be recognised that suppliers often have innovative ideas to improve their own and their customer’s service. However suppliers can be blocked in their attempts to put these ideas forward.
You should want to be a customer of choice i.e. suppliers will invest and bring innovation to the contract. You should adopt these behaviours and allow supplier innovation and added value activity to flourish:
Quickfire Guide
Embrace your suppliers as an extension of your business. Learn from their ideas and build open and trusting relationships where innovation will thrive.
Establish a culture of trust and encourage ideas from suppliers, as they often know your business better than some of your own team.
Define and share your Organisation's definition of supplier innovation. This way suppliers can understand your internal process, where they fit in and your expectations of them.
Share as much information as you can with your top suppliers. The earlier suppliers can see your product / services roadmap, the sooner they can provide ideas to improve it.
Implement a consistent governance framework. If a supplier’s idea has potential, assign an internal owner to investigate and develop this ensuring there is accountability and development continuity.
Innovation does not have to be ‘ground breaking’. Even minor service or process adjustments can bring cost and/or efficiency gains.
Encourage collaboration within the teams. Let them know there will be some ideas that will be more successful than others, but all ideas will be considered. Publicise and reward innovative contributors appropriately.
Publicise supplier innovation success stories. A brief email outlining real supplier initiated added-value and the mutual benefits will encourage others to do the same.
Consider innovation as a standard KPI and ensure innovation is on the agenda at performance reviews.
Innovation is a two way process. Your organisation should be equally active in exploring innovative ideas which will help your suppliers improve their performance and service delivery.
Demand Management can be defined as:
“the alignment of a business’ consumption with its business requirements”
It is applicable to all goods and services where internal demand and consumption can be influenced to reduce costs.
Demand Management is a key aspect of effectively aligning external resources to meet requirements. When Demand Management is considered, it is often seen as a simple matter of stopping people spending money. However there are ways to look at Demand Management without completely preventing spend. These can provide notable savings and have a less drastic impact on the business.
Demand often results from internal practices and processes rather than from addressing a real need of the Organisation. The approach is about addressing change ‘in’ an Organisation. Therefore the starting point will be the culture, policy and behaviours of your Organisation.
Your Organisation can also participate by sharing best practice, benchmarking behaviour, creating policy guidance and undertaking peer review.
Demand Management can come at different points in the procurement process. For example, during the initial purchase point e.g. that software licences are purchased for the correct number of users at a single point in time. Demand Management can also occur in situations where costs are recurring as an ongoing activity such as in a category where spend is ongoing and regular (e.g stationery or postal services).
Demand Management, including behaviour change, represents a significant and untapped opportunity.
In the short term |
changing expectations |
in the medium term |
changing participation |
in the long term |
reducing need |
There are 3 main principles of demand management:
1. Each business unit should have exactly what it needs in order to deliver its business objectives;
2. Any resources consumed above this level represents a waste to the Organisation;
3. There may be many and very different ways of meeting a user's needs. Each way represents a different level of resource to achieve the same outcome.
The three strategies listed below could be independently or jointly applied.
Is the requirement really needed? Can the consumption be stopped? e.g. cancel non-essential meetings, or stop the use of mobile phones for non-business calls. |
|
Replace |
Can we use lower cost or more effective alternatives? e.g. use video-conferencing for meetings or ensure non-confidential papers are not treated as confidential waste |
Reduce |
Can we use less of a product / service? e.g. don’t order a monitor with every PC purchase or, schedule meetings for the same day |
With Demand Management you should consider:
There are a number of benefits to an effective Demand Management strategy. Many benefits are driven by:
When robustly implemented across all goods and services Demand Management drives public sector Organisations’ efficiency and effectiveness. The Organisation uses all the external resources it procures to meet operational requirements.
The Demand Management process challenges the norms, standards, customs and practices of an Organisation. This is done to a degree not usually found in other processes.
Using Demand Management to prepare Strategic Sourcing, you can establish that the Organisation's requirements are sourced to a very specific level. This can avoid the development of a sourcing strategy for over-specified operational requirements.
Used routinely Demand Management can ensure the highest possible resource levels are directed at front line services. This is especially important in the public sector.
Consideration as to how the demand will be forecasted and fluctuations managed should be initially undertaken at the ‘Shaping the Requirement’ stage. This should be subsequently monitored and managed throughout the lifetime of the contract. Failure to do so could result in:
Effective Demand Management forecasts also give the supply base the opportunity to manage their costs. This can be achieved by positioning resource and materials in line with demand.
Demand forecasting should be based on considerations such as:
Where practical, you should look to reduce future demand and costs by using strategies such as:
For any supplier to operate effectively, it must understand and manage its demand. They can use this knowledge to tailor its resources and processes proportionately. This will ensure they deliver their service in the most efficient and cost effective manner. By understanding historical demand, an organisation can work with its suppliers to realise mutual cost and efficiency gains.
The most effective way to forecast future demand is to consider a combination of:
Forecasting is not an exact science and will never be 100% accurate. However these elements should provide sufficient information to allow the Organisation to develop forecasts. These forecasts should be accurate enough to accommodate demand fluctuations during the lifetime of the contract(s) with minimal cost.
The Organisation should ensure the supplier stays in regular contact with all key stakeholders (including other suppliers). This will ensure that all parties are aware of the supply/demand position, especially during periods of fluctuation.
Performance Review Meetings provide your Organisation and the supplier with an opportunity to:
The Performance Review Meeting standard agenda template can be completed by your Organisation and the supplier before the meeting. This will provide a structure to the meeting.
It is best practice to hold at least an annual review for suppliers identified (under the segmentation process) as requiring ‘medium level’ supplier management. At least two review meeting per year should be held for ‘high level’ suppliers.
The Review Meeting Template and a meeting agenda example are available below to assist you in doing this.
The Performance Review Agenda Example (agenda can be amended to suit your personal preferences):
Quickfire Guide
Agenda Item |
Description |
Introduction and Opening Remarks |
Introduce attendees. Recognise special or new guests. Provide any opening remarks that are pertinent to this meeting such as current events, organisational changes, etc. |
Review of Action Items |
Each Performance Management Review meeting will produce some follow up action items for your supplier, your Organisation or both. These should be documented and followed up at the next Performance Management Review meeting. |
Supplier Performance
|
Performance against SLAs/ KPIs/ Scorecards should be reviewed and discussed, and any performance concerns raised. This will be a quick review if all deliverables are being achieved. Any "below plan" performance will demand more discussion and most likely recovery action plans. These plans should be managed operationally and reviewed at the next Performance Review meeting. |
Customer Performance
|
The supplier can raise any customer performance issues. For example these may be impacting their ability to their contractual obligations. |
Key Improvement Areas/ Opportunities |
All opportunities for improvement should be explored. Once identified, action plans should be agreed. Areas to be explored should include: current performance issues, cost, process, Sustainable Procurement, Corporate and Social Responsibility, innovation/value add. |
Supplier Presentation |
The supplier should provide a business overview, including example financial information, strategy, overarching objectives, etc. |
Meeting Summary and Review of Action Items |
Round up of meeting and confirm next meeting date. |
(file type: docx)
(file type: docx)
(file type: docx)
(file type: pdf)
(file type: docx)
(file type: docx)
(file type: xlsx)
Why embed Contract & Supplier Management
Persuading stakeholders to implement change can be difficult. This is particularly true if there are no absolute, cast-iron guarantees to support the proposal. Therefore you must consider how to show the potential benefits of an embedded Contract & Supplier Management (CSM) model.
The guidance below and the linked templates should help you build the necessary business case / justification.
Cost savings, for both the supplier and your organisation could be a CSM benefit. Significant cost saving can be achieved through an increased and embedded focus on CSM.
Another approach is to consider the risks and missed opportunities of not focusing on CSM, for example:
Consequently, CSM is unlikely to be effective unless the parties move from a transactional to a relational model. This could actively encourage and develop close working relationships and resulting mutual benefit(s).
The success of the relationship between an organisation and suppliers/service providers depends on the extent to which there is:
You need to build the relationship outside of the traditional constraints of a performance-based contract. A 'we are in this together’ approach should be fostered. This will encourage open communication and maximise service and cost efficiencies.
To succeed, build on small success: when a pattern of small successes has been achieved, proposing a more ambitious CSM plan becomes less daunting. This is because you have proven results to refer to.
Instead of leaping into the unknown, it becomes the expansion of an already successful process. Initial small successes are a recognised option to create awareness and buy-in for the larger initiative. Small projects are likely to be the best way to gain the support necessary for broader, organisation-wide embedded CSM model adoption.
The selection of small project(s) is important. It should be contracts or services not in crisis and which have scope for improvement. It is even better if it is a contract or service where stakeholders have voiced concerns or expressed a desire to seek improvements.
Once the contract/service has been agreed, a small cross-functional team should be created under a nominated contract manager who will own and manage the small project.
As laid out in more detail throughout the CSM guidance, the nominated cross- functional team should:
Once the desired outcomes are agreed, your nominated contract manager should ensure maintained focus within both organisations until they have been achieved and delivered. The results should be used to demonstrate the untapped potential open to a focused CSM approach.
The Business Case Template, found at the bottom of this page contains some ideas you may wish to include and should help lay out the business case. Your Organisation may have a standard template to use.
Managing the supplier contractual relationship requires a discrete set of responsibilities and activities. As a result this should be the responsibility of a nominated member of staff. An organisation should consider how to ensure that:
These considerations should be built into the commodity/service specification and/or the terms and conditions of the contract.
Your Contract Manager should be engaged early in the process. This will ensure they engage early with stakeholders and determine the appropriate contract service level requirements and Key Performance Indicators. Service level and KPI requirements should have been included in the tender documentation.
For Care and Support Services processes must not duplicate those of the Care Inspectorate.
The care manager is the role which has overall responsibility for ensuring that the totality of care and support for an individual is achieving the desired outcomes.
Determining the resource required to manage the contract portfolio/supplier base is not an exact science. Very often it is subjective.
Any organisation planning to transition Contract and Supplier Management responsibilities to an embedded CSM team, must estimate the resource required. You should invest time too realistically and pragmatically plan required resources.
Some resource planning options are laid out below.
Resource planning for a new CSM team often depends upon the judgment of an experienced manager. You should provide enough information for an experienced manager to make an initial estimation of the extent of work required i.e. to manage the volume of Leverage, Routine, Strategic and Bottleneck suppliers.
A decision may be made to start with a small selection of critical and/or problematic suppliers. Then you may gradually incorporate more contracts/suppliers with additional resource coming on board as appropriate.
The Resource Planning Tool, found at the bottom of this page, is taken from a particular Scottish public sector organisation’s successful proposal to transition from a traditional ‘let & forget’ model to a CSM model (and is indicative only). For the avoidance of doubt, this organisation absorbed the workload into the existing headcount by reallocating/reprioritising responsibilities and eliminating non-value add activity.
Quantification / Segmentation
Quantification / segmentation is the most accurate methodology of estimating the resource required to manage the contract / supplier portfolio. It is however, still an ‘estimation’ as many factors can affect the resource requirements, such as:
You need to identify the strategic positioning of your contract. The Strategic Positioning Tools found in the Develop Commodity/Service station can assist you in doing this.
Regardless of how formal a commodity/service strategy is, or is not, there is always thought and decision making on:
A straightforward way of assessing the potential level of CSM required is to consider the:
Please find below the Segmentation Tool document at the bottom of the page. This segments the contract portfolio into four categories (Leverage, Strategic, Bottleneck, Routine), which will allow an organisation to estimate the extent of work involved in managing each category.
Scorecard
Please find below the Full Balanced Scorecard. The balanced scorecard can be edited to suit the commodity/service area.
The Resource Tool, which can be be found at the bottom of this page, can be used to help you estimate the amount of resource required for your contract management needs.
Please find below the Contract Management Supply Positions Tool. This document helps you segment your contract portfolio into four categories (Leverage, Strategic, Bottleneck, Routine). This will allow your organisation to record the extent of work involved in managing each category. This includes frequency of performance review meetings and frequency of Management Information, etc.
This tool will provide an estimated resource calculation. There is a natural tendency to over-estimate the work required and it is important to avoid this by being as pragmatic as possible. It is worthwhile comparing/collaborating with a similar organisation which has a more mature CSM operation. Especially where an organisation lacks the experienced managerial staff required to make informed judgements. This collaboration will allow your organisation to benefit from the mature organisation’s experience You will factor in distortions such as the learning curve they experienced on the journey towards maturity.
Roles and Responsibilities
Board / Senior Management sponsorship is critical to the success of an embedded Contract and Supplier Management approach.
The Board / Senior Management Team should take the ultimate strategic ownership of business critical strategic supplier(s). They should be fully committed to improving contract performance collaboratively with those suppliers.
Every contract should be managed by a nominated member of staff (‘contract manager/contract management officer’). In a collaborative setting, organisations should determine which organisation will take the lead in managing the contract. An organisation should ensure that there is clarity about the distinction between:
The Contract Manager/Contract Management Officer should have the mind-set to exceed rather than meet required goals. They will, deal with a constantly changing set of requirements. They need excellent communication and stakeholder management skills. They should be the principal owner of the supplier relationship and contract performance. They will be responsible for business-to-business relationships, contract management performance and contract management competencies, including:
Contribute to contract and supplier management process by:
(file type: docx)
(file type: docx)
(file type: docx)
(file type: docx)
(file type: docx)
(file type: docx)
(file type: docx)
(file type: xlsx)
Where you have not built an electronic catalogue as part of the tender process and the commodity/service is deemed to be made into a catalogue, you should set up the successful tenderer on the Pecos Content Management System (PCM) to ensure that you can prepare the catalogues.
The process of content management from start to finish can take weeks, mainly dependent on the size (number of line items) and the number of catalogues involved.
Quickfire Guide
You will need to:
The above should be done before finally issuing to the end user organisations.
It is essential to allow enough time in your process for these tasks to be completed prior to the date that the contract or framework is required to be active.
Below are the key considerations for communicating the contract. These should be considered in your communications plan.
Having completed the procurement to the point of award it is essential to communicate effectively. Communication of the Contract Award and of the subsequent procedures is essential to ensure compliance. It also maximises the planned benefit(s) from the procurement exercise.
You must know who you are targeting with your communications. During strategy development you should have identified all key stakeholders from suppliers to end users. You should consider communications in terms of the three areas below, for each of the identified stakeholder groups.
What is your communication about? Be clear on your key and supporting messages. Ensure that the subject is appropriate for the audience (stakeholder group). Ensure the communication stays focused on what they need to know and what is expected of them.
Plan and consider your communications timings carefully, in line with the implementation process. Your communications must:
Communication should take place at the start, throughout and end of the process. .
You must consider how you communicate to your audience. This can be determined by the stakeholder audience you are targeting.
You may also wish to consider (but not limited to):
Newsletters- stakeholder community;
Intranet/internet article - public audience
e-zines – targeted group;
e-mail - small targeted group;
Roadshows – specific bidders or the general supplier community.
Accessibility requirements of your audience and accessibility legislation should be considered.
Some activities undertaken are described more fully further along this process e.g. buyer/end user information packs, supplier buyer events.
This is intended as a guide rather than being prescriptive.
Communication with people who use services and their carers
Having finalised and agreed the procurement plan, an organisation should communicate its intentions to people who use the services and also their carers/representatives. It is important that an organisation provides clear and unambiguous information at this stage and that this information is tailored to the particular audience.
In these communications an organisation should explain:
An organisation should also provide contact details for further information.
An organisation should ensure that people who use services and also their carers have help to understand the process and what, if anything, they are being asked about. It should also ensure that these people have sufficient time to consider how they might be affected and to formulate their views before having to respond
Transitional arrangements
It is important that this stage of the procurement process is managed successfully to ensure minimum disruption to people who use services and their carers. This will require close co-operation between different teams within an organisation and between it and service providers.
This is particularly important where the outcome of the procurement exercise involves the transfer of an existing service to a new service provider. This is because there is some potential for the transfer process to be demanding and consume significant amounts of staff time. An organisation should facilitate the transfer of accurate, up to date information to the new service provider and ensure that the handover arrangements are appropriate and fully implemented.
Service providers will need to satisfy the Care Inspectorate that it can adhere to the Public Services Reform (Scotland) Act 2010 and Regulations and also meet the relevant National Care Standards. The Care Inspectorate can take up to approximately six months to register a new care service. This depends on a range of issues, including provision of a competent application and the complexity of the service being provided.
Where an existing service provider seeks to deliver a new service under the existing registered care services, this should be discussed with the Care Inspectorate. It may be possible to vary the registration to include the new contract. However, consideration would need to be given to: the current conditions of registration; the size of the service; management and staff support arrangements; geography; client group and needs of those people who use services; transferability of staff across the service; staff skills and training; and the aims and objectives of the service.
If a service provider applies to cancel its registration, it is legally required to state whether notice has been given to those people who use the services and their carers about the changes to its service and how their needs will be met if the application to cancel is approved by the Care Inspectorate. An organisation should provide the necessary support and information to a service provider to enable it to meet its legal obligations.
An organisation which is outsourcing a service or bringing a service back in-house will have to meet its legal obligations under the TUPE Regulations. It should, in all such cases, seek legal advice on application of the TUPE Regulations. In other cases involving the transfer of an existing service, an organisation should consider whether it needs to take any action, for example to facilitate the exchange of information between service providers, should the TUPE Regulations apply.
The first meeting with the successful supplier should be held as soon as possible after contract award.
The purpose of this meeting is to:
You must keep in regular contact with the supplier during the contract implementation phase, scheduling additional meetings and communications.
You may wish to create an information pack for organisations and/or users which contains key contract information including:
This information pack should demonstrate how the contract delivers best value and provides information on contract benefits e.g. savings, KPIs, improvements in quality and service, prompt payment of the full supply chain, sustainable procurement and community benefits expected etc.
An example of an information pack is the Postal Services End User Guide below. This is a detailed example. Every information pack must be proportionate to the size and complexity of the procurement, therefore your information pack may be much smaller.
A useful way to raise contract awareness amongst potential customers is to organise Supplier/Buyer events. This gives both parties an opportunity to meet each other and exchange information e.g. undertaking a Supplier/Buyer Event Presentation, and/or distributing information packs / buyers’ guides.
Such events can provide useful information which can be used in the current contract (assuming it does not cause a material change) or in future contracts.